Mine surveying technique and steel storage tank base deformation removal

2021

Full text Open access: Gold Metadata (CSL-JSON)
DOI 10.21440/0536-1028-2021-7-69-79
Data confidence 70 medium
How this score is calculated

It is built from checkable properties of the record itself: whether the article has a DOI, how many independent sources confirmed its data, whether the required fields are filled in, and how recent the latest confirmation is. Disagreement between sources and a missing identifier lower it. A value of 80 or above means the record was published without further checking; 60 to 79 means it is published at reduced confidence, with a manual check advisable. A record verified by an editor by hand is never pushed below 90 by a recalculation. This scores our data about the article, not the article itself.

Abstract

Introduction. Vertical steel tanks are extensively used in oil fields to hold crude oil and other liquids. Their construction requires continuous surveying control. However, measurement procedures, data processing, and deviations and documentation correction are not universal and cannot be applied for tanks with a capacity of less than 3000 m3. Moreover, the process of correcting the detected bottom irregularities is poorly substantiated and intuitive. Research objective is to improve the as-built survey accuracy and reliability of the low-capacity steel tank bottom, substantiate the minimum height of its irregularities, increase the objectivity and productivity of measurement processing, develop an unambiguous method for time-predictable correction of bottom irregularities, and substantiate the optimal contents of its relief’s as-built scheme. Methods of research. Geometric leveling for the bottom profile survey failed to provide adequate accuracy and was therefore replaced by the method of trigonometric leveling. A method has been developed for determining the deviations of the existent tank bottom profile from the design position by means of algebraic actions with surfaces of a topographic order. The accuracy of determining the smallest height of bottom irregularities has been estimated under the tacheometric survey. A method has been proposed for controlling the correction of tank bottom irregularities based on evaluation calculations of bottom deformations by the finite element method. Research results. All the development results are exemplified by a specific production example. It was found that for a full completion of work, two iterations of tank bottom irregularities correction are enough. Methods of optimal design for the facility’s as-built schemes are presented. Conclusions. A simple, accurate, low-cost, productive, and time-predictable method of mine surveying, mathematical processing and correction of deviations in the tank bottom profile has been developed. This technique reduces the construction period and increases the operating time of the facility.