Experimental data on the IVG.1M RCCS influence on the reactor downtime between start-ups

Eurasian journal of physics and functional materials, 2022

Full text Open access: Gold Metadata (CSL-JSON)
DOI 10.32523/ejpfm.2022060304
Data confidence 70 medium
How this score is calculated

It is built from checkable properties of the record itself: whether the article has a DOI, how many independent sources confirmed its data, whether the required fields are filled in, and how recent the latest confirmation is. Disagreement between sources and a missing identifier lower it. A value of 80 or above means the record was published without further checking; 60 to 79 means it is published at reduced confidence, with a manual check advisable. A record verified by an editor by hand is never pushed below 90 by a recalculation. This scores our data about the article, not the article itself.

Abstract

The paper describes an experience of the IVG.1M research reactor operation with the core water-cooling system, which includes an auxiliary reactor coolant cooling system, designed for forced coolant cooling in periods of long-term reactor shutdown. The IVG.1M reactor is cooled by a limited amount of coolant circulating in a closed circuit, heated and uncooled during reactor operation. In this regard, duration of continuous operation of the reactor and frequency of startups are restricted due to limited value of water temperature at the core inlet. Prior to commissioning of the reactor coolant cooling system, it was cooled by means of natural heat transfer to the environment, while full-scale reactor startups were conducted with a frequency of approximately once per month. With forced coolant cooling, provided by use of the reactor coolant cooling system, its temperature decreases to acceptable values approximately within a week after the next startup, and, accordingly, full-scale startups of the IVG.1M reactor can be conducted once a week. This significantly expands potential of using the reactor and at the same time accelerates burnup of nuclear fuel and decrease in the reactor reactivity margin. Estimation of the fuel burnup rate will allow organizing timely supply of fresh fuel to replace the burnt out fuel. The paper contains the measurement results of the coolant temperature after a series of reactor startups, based on which it can be concluded that the IVG.1M RCCS has an effect on reducing the reactor downtime time between startups. The obtained results can be used to select and justify options for implementing the reactor campaign and its fuel.