Methodological approach to creation of the 3D model of an oval-shaped open pit mine

2019

Full text Open access: Gold Metadata (CSL-JSON)
DOI 10.1051/e3sconf/201912301049
Data confidence 70 medium
How this score is calculated

It is built from checkable properties of the record itself: whether the article has a DOI, how many independent sources confirmed its data, whether the required fields are filled in, and how recent the latest confirmation is. Disagreement between sources and a missing identifier lower it. A value of 80 or above means the record was published without further checking; 60 to 79 means it is published at reduced confidence, with a manual check advisable. A record verified by an editor by hand is never pushed below 90 by a recalculation. This scores our data about the article, not the article itself.

Abstract

A 3D model of optimal contours phased development of oval-shaped open pit mines is proposed in the article. It is assumed that with enough accuracy the volumetric contour of the open pit mine is interpolated by an elongated elliptic hyperboloid. The calculation formulas for mineral resources are derived and optimal volumes of overburden are determined depending on the mining phase. In this case, the total number of mining phases is set in advance. The stripping ratio is used as a quality criterion of the optimization task. The problem of optimal control is solved using the Bellman function in dynamic programming. All the necessary calculation formulas are obtained in the final form by solving the optimization problem. Their simplicity and substantiation of each conclusion ensure that the results of this study can be successfully applied in practical calculations of the design and planning of mining operations in open pit mining.